www.windpoweringamerica.gov/docs/farm_bill_small_wind_tech_worksheet.doc

50%">

Document Checklist


First Name:


Middle Initial:


Last Name:


Zip Code:


Company/Organization (if applicable): 


Project Name: 



Attach the following documentation:


1.  Describe project site.  Preferably
attach a one page color site map. Must indicate location of wind turbines,
structures or trees, inverter batteries (if any), lockable disconnect
switch, and point of connection with the utility system.


2.  Annual average wind speed and wind direction
(documentation and data source)........


3.  Estimated annual energy output (attach documentation
and methodology)...


4.  One-line diagram for electrical interconnection


5.  Optional, but helpful, site photos. Preferred
method is to take a series of photographs from the proposed turbine
location.  Rotate 360 degrees clockwise taking pictures every 46
degrees. Indicate predominate wind direction on one photo.......


Section a: Qualifications of key service providers.


Company/Organization Name: 


First Name:           
Last Name:              
Title:


Daytime Phone (include area code):                
Web Site: 


Mailing Address: 


City:      
State:       Zip: 


Function: 


Last manufacturer workshop attended:


Credentials and years of related experience:   


Number and type of similar systems installed:



 

Company/Organization Name: 


First Name:           
Last Name:              
Title:


Daytime Phone (include area code):                
Web Site: 


Mailing Address: 


City:       State:      
Zip: 


Function: 


Last manufacturer workshop attended:


Credentials and years of related experience:   


Number and type of similar systems installed:



 

Company/Organization Name: 


First Name:           
Last Name:              
Title:


Daytime Phone (include area code):                
Web Site: 


Mailing Address: 


City:       State:      
Zip: 


Function: 


Last manufacturer workshop attended:


Credentials and years of related experience:   


Number and type of similar systems installed:



 

Section b: Agreements, permits, and certifications.


(1) Identify all required building
agreements and permits:


Building                                       


have permit attached initiated needs to be sent none required


Electrical


have permit attached initiated needs to be sent none required


Zoning                                         


have permit attached initiated needs to be sent none required


Other                                           


have permit attached initiated needs to be sent none required



(2) Interconnection agreements and tariff arrangements:


Interconnection agreement...completed attached initiated needs to be sent none required


Tariff arrangement..completed attached initiated needs to be sent none required


Utility name: 


Describe plans for meeting utility requirements,
if applicable: 



(3) Environmental:


Are there any additional environmental concerns that
are not previously identified on Form RD 1940-20?


Yes     No


If yes, describe:



Section c:  Resource assessment.


Average annual wind speed:  (mph or m/s) 
Height at reference point:    (m or ft)  


Wind direction:      
Wind Speed:       Elevation: 


Estimated annual energy output*: 
kWh


*Please attach documentation and methodology
used for calculating estimated annual energy output. 



Section d:  Design and engineering.


Turbine:


Wind turbine manufacturer: 


                        


Manufacturers web site address: 


       


Turbine Model: 



Number of similar model turbines sold by manufacturer: 


Wind turbine rated power: 


Wind turbine peak power: 


Wind turbine output voltage: 


Number of turbines for this project: 


Total wind system output:                  
(No. of turbines x power output rating)


Turbine rotor diameter:                      
(ft. or m)


Tower:


Tower height:                                    
(ft. or m)


Manufacturer Type:                                      guyed     tilt up     self supporting


Inverter:


Inverter manufacturer:                       


Inverter model: 


Number of inverters: 


Inverters continuous AC rating:                          


Total inverter output (Inverter continuous AC rating
x number of inverters): 


Battery:


Battery model: 


Battery voltage:  Volts    
Amp-hour rating (20 hour rate)


Number of strings: 


DC bus voltage:  Volts


Turbine controller model (if applicable): 


Diversion load power rating (if applicable): 



System type and mode of operation:
(check applicable)


  Utility interactive (parallel/capable of backfeeding
the meter)


  Utility interactive with battery backup (capable
of backfeeding the meter)


  Dedicated circuit, utility power as backup
(transfer switch)


  Dedicated circuit, battery charging, utility
power as backup (transfer switch)


  Stand-alone (system confined to an independent
circuit, no utility backup)


  Stand-alone with battery backup (system confined
to an independent circuit, no utility backup)


Section e: Project development schedule.


Check boxes to indicate activity:


Month


1      
2       3      
4


   5      
6      7      8


  9     
10     11    12


Approved permits & permits