Implementation of a Distributed Control System for Electric ...
Implementation of a Distributed Control System for Electric Distribution Circuit Reconfiguration
Dean Craig, Member, IEEE And Craig Befus, Member, IEEE
IEEE T&D Conference 2006
Presentation Overview
· IntelliTEAM II Description · ENMAX DA Project · Project Goals and Scope · System Components and Architecture · Example Restoration Events · Current Project Status and Results · Conclusion
IEEE T&D Conference 2006
2
IntelliTEAM II Logic Description
· Fault interrupting device opens (breaker or · ·
recloser) Sectionalize: Open switch(es) to isolate fault and prepare for restoration of unfaulted segments Restoration: Communicate then close switches to re-energize unfaulted segments
IEEE T&D Conference 2006
3
IT-II Sectionalizing Logic
·
The switch control sees a fault · Fault current threshold exceeded · Fault duration time met · Count incremented with subsequent loss of voltage · Open when count reached The switch control sees a 3Ø voltage outage · Voltage falls below LOV threshold · Open when count reached on voltage loss · Open when loss of voltage timer expires Switches open to sectionalize after a fault is interrupted by an upstream breaker or recloser
·
·
IEEE T&D Conference 2006
4
IntelliTEAM II Application
Teams coordinate actions to automate systems of any size
IEEE T&D Conference 2006
5
IntelliTEAM II
Team structure · A team consists of the switches bounding a feeder segment · Switches can belong to one or two teams · A team may have one to eight switches · A team may have up to 8 sources · Teams are building blocks
IEEE T&D Conference 2006
6
IntelliTEAM II--Teams
· ·
Distribution feeder segment bounded by switches Types of Teams or feeder/line segments
Defined as automated switch
Simplest segment
Up to (8) switches
IEEE T&D Conference 2006
7
IntelliTEAM II Switch Definitions
·S/S source sub ·S source ·L/T load tie ·T - tie ·T/S tie sub ·L - load
T/S
S/S
S
L/T L
T
IEEE T&D Conference 2006
8
IT-II Restoration Logic
· Team concept · Coach metaphor · Know why your team mates opened · Verifies there is no fault in the segment · Verifies fault is isolated · Verify load in segment to be restored will not ·
exceed capacity available Agree to close a switch
IEEE T&D Conference 2006
9
IT-II Restoration The Coach
· Travels between all switches in a team · Distributes data and coordinates operation · Visits each team member within prescribed time · ·
period · Carries ID number and visit counter When an event occurs, team member tells all in the team and the coach Grants permission for closing a switch · Meets with the coach of adjacent teams to decide when to close switches
IEEE T&D Conference 2006
10
IntelliTEAM II "Ready"
· Team has to be in "Ready" · If automatic operation is disabled or has certain · ·
problems, the control and all associated teams are out of ready. Loss of communications between team members takes the team out of ready. You can take the team out of ready on purpose · Automatic operation disable/enable · Prohibit restoration (DNP command)
IEEE T&D Conference 2006
11
About ENMAX
· · · · ·
1,044-square-km service area includes City of Calgary and surrounding area 33 substations served at 138kV and 69kV 25kV and 13.2 kV Distribution Systems 395,000 customers System peak demand: 1,401 Megawatts
City of Calgary
IEEE T&D Conference 2006
12
Project Goals
· Achieve and maintain first-quartile reliability
performance as measured by SAIDI and SAIFI vs. peer Canadian utilities
· Meet regulatory requirements by improving the
reliability of the worst performing circuits on the system and by operating the distribution system in a safe and reliable manner
IEEE T&D Conference 2006
13
Project Scope
· Five year program will automate all 25 kV feeders
and the worst performing 13 kV feeders in the ENMAX service territory
· Full build-out will automate ~80 feeders using ~200
automated load-break switches
IEEE T&D Conference 2006
14
SAIDI Improvement Goal
ENMAX - Interruption Duration per Year
1.00 0.90
0.80 0.70 Duration per year 0.70 0.66 0.64 0.60 0.65 0.62
0.59
0.50 ENMAX - Yearly Data 0.40 ENMAX - Required Projection
0.30
0.20 1995 1996 1997 1998 1999 2000 YEAR 2001 2002 2003 2004 2005 2006
IEEE T&D Conference 2006
15
SAIFI Improvement Goal
ENMAX - Interruption Frequency per Year
1.80 1.70 1.60 1.50 1.40 Frequency per year 1.30 1.20 1.10 1.00 0.90 0.80 0.70 0.60 0.50 1995 1996 1997 1998 1999 2000 YEAR 2001 2002 2003 2004 2005 2006 ENMAX - Yearly data ENMAX - Required Projection 1.10 1.08 1.00 0.90 0.80 0.71
IEEE T&D Conference 2006
16
System Components
Components of the S & C system are:
· · · · · · ·
Scada-Mate overhead switches Motor operated RS-PMH pad-mount switches IntelliTEAM II control system UtiliNet spread spectrum radios S&C Proxy Server WinMon Configuration Software Substation Logic Module
IEEE T&D Conference 2006
17
System Components
UtiliNet Spread-Spectrum Radio Network
· · · · ·
No radio licence required 900 MHz frequency band Connectionless mesh network Enables Peer to Peer communications "Smart" data packet routing (Self-healing Network) Highly scalable network
IEEE T&D Conference 2006
18
System Components
S & C Proxy Server
· Resides in ENMAX Control Centre · Interrogates all IntelliTEAM II devices and caches · ·
data in real-time database Serves real-time data to EMS Master-Station and Substation Logic Module Enables WinMon remote configuration of all IntelliTEAM II devices
IEEE T&D Conference 2006
19
Substation Logic Module
· Required to automate feeder segment closest to · ·
substation on feeders with electro-mechanical relay Prohibits IntelliTEAM II restoration on feeder when substation recloser blocked or during under-voltage or under-frequency event Central location reduces equipment and installation costs
IEEE T&D Conference 2006
20
Substation Logic Module
IEEE T&D Conference 2006
21
Substation Logic Module
IEEE T&D Conference 2006
22
System Architecture
IEEE T&D Conference 2006
23
Operator Interface
IEEE T&D Conference 2006
24
Operator Interface
IEEE T&D Conference 2006
25
Operator Interface
IEEE T&D Conference 2006
26
116 114 112 115 113
25-11.112_C1
114 112 118 111
Phase I & II Feeders and Substations
IEEE T&D Conference 2006
111 115 114 116 113 117
25-39.116_A
27
Project Status- 2004
· · · · ·
Phase I completed in early 2004 Eighteen 25kV feeders automated (7% of system) Eleven outage events on these feeders in 2004 Automation system saved an estimated 862,000 customer outage minutes and 6,800 customer outages Resulted in 8.6% SAIDI and 1.7% SAIFI reduction for 2004
IEEE T&D Conference 2006
28
Project Status 2005
· · · · ·
Phase II completed in summer 2005 Ten 13kV feeders automated (11% of system) Twelve outage events on automated feeders in 2005 Automation system saved an estimated 987,000 customer outage minutes and 30,800 customer outages Resulted in 13.1% SAIDI and 13.0% SAIFI reduction for 2005
IEEE T&D Conference 2006
29
Project Status 2006
· · · · ·
Phase III installation in progress Two 25kV and Fourteen 13kV feeders selected Nine outage events on automated feeders year to date Automation system saved an estimated 901,000 customer outage minutes and 20,900 customer outages Resulted in 19.6% SAIDI and 18.5% SAIFI reduction Year to Date
IEEE T&D Conference 2006
30
Project Status Future
· Phase IV 2006 · Phase V - 2007
IEEE T&D Conference 2006
31
Outage Event Example 1
111 9
43
45
44 65 36
IEEE T&D Conference 2006
32
37
Outage Event Example 1
111 9
Fault
43
45
44 65 36
IEEE T&D Conference 2006
33
37
Outage Event Example 1
1. Substation Breaker Locks Out
111 9
Fault
43
45
44 65 36
IEEE T&D Conference 2006
34
37
Outage Event Example 1
1. Substation Breaker Locks Out 2. IntelliTEAM II opens Switches 9, 43, and 44
111 9
Fault
43
45
44 65 36
IEEE T&D Conference 2006
35
37
Outage Event Example 1
1. Substation Breaker Locks Out 2. IntelliTEAM II opens Switches 9, 43, and 44 3. IntelliTEAM II Closes Switch 65
111 9
Fault
43
45
44 65 36
IEEE T&D Conference 2006
36
37
Outage Event Example 1
1. Substation Breaker Locks Out 2. IntelliTEAM II opens Switches 9, 43, and 44 3. IntelliTEAM II Closes Switch 65 4. IntelliTEAM II Closes Switch 44
111 9
Fault
43
45
44 65 36
IEEE T&D Conference 2006
37
37
Outage Event Example 1
1. Substation Breaker Locks Out 2. IntelliTEAM II opens Switches 9, 43, and 44 3. IntelliTEAM II Closes Switch 65 4. IntelliTEAM II Closes Switch 44 4. IntelliTEAM II Closes Switch 43 Elapsed Time: 37 seconds Customer Outage Minutes Saved: 58,450 Customer Outages Saved: 1,670
111 9
Fault
43
45
44 65 36 37
IEEE T&D Conference 2006
38
Outage Event Example 2
Pole Fires, March 16, 2006
IEEE T&D Conference 2006
39
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
40
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
41
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
42
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
43
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
44
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
45
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
46
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
47
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
48
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
49
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
50
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
51
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
52
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
53
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
54
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
55
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
56
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
57
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
58
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
IEEE T&D Conference 2006
59
117
115
Outage Event Example 2
118
116
114
112
115
113
114
112
111
114
116
113
419,050 Customer Outage Minutes Saved 8,870 Customer Outages Saved
IEEE T&D Conference 2006
60
117
115
Conclusion
·
Distributed Control is a good fit for feeder automation · Distributed approach simplifies complex control problem · Highly scalable · Minimal infrastructure requirements The ENMAX project demonstrates successful deployment of a large scale, fully automatic system Significant reliability improvements have been realized
· ·
IEEE T&D Conference 2006
61
Questions?
IEEE T&D Conference 2006
62
enmax.com
IEEE T&D Conference 2006
63