MN electric rate - Standby Service - C-10M

rial size=-1 color=black> Below is a cache of http://www.otpco.com/ElectricRates/PDF/MN/c-10m.pdf. It's a snapshot of the page taken as our search engine crawled the Web.
The web site itself may have changed. You can check the current page or check for previous versions at the Internet Archive. Yahoo! is not affiliated with the authors of this page or responsible for its content.
MN electric rate - Standby Service - C-10M Otter Tail Corporation d/b/a

OTTER TAIL POWER COMPANY
Vol. I, Sheet 40
Fergus Falls, Minnesota
Rate Designation C-10M, Page 1 of 8
ELECTRIC RATE SCHEDULE
Third Revision



MINNESOTA PUBLIC
EFFECTIVE for services rendered on
UTILITIES COMMISSION
and after, November 30, 2007, in MN
Docket No. E-017/GR-07-1178

Approved: November 27, 2007
APPROVED: Bernadeen Brutlag


Manager, Regulatory Services


STANDBY SERVICE



OPTION A: FIRM OPTION B: NON-FIRM

On-Peak Off-Peak On-Peak Off-Peak


Transmission Service
927 928 937 938
Primary Service
923 924 933 934
Secondary Service
925 926 935 936


APPLICATION OF SCHEDULE
:
This schedule, including Attachment 1 - Definitions, provides
Backup
, Scheduled Maintenance, and Supplemental Services, is applicable to any customer who
has the following conditions:

1.
Requests to become a Standby Service Customer of the Company. Otherwise, the
Company views the Customer as a Non-Standby Service Customer. For information about
the different categories of Non-Standby Service customers, including exemptions from
Standby Service
, please see Attachment No. 1 Definitions.
2.
Utilizes Extended Parallel Generation Systems to meet all or a portion of electrical
requirements, which is capable of greater than 60 kW. Customers with Extended Parallel
Generation Systems
used to meet all or a portion of electrical requirements that are capable
of 60 kW or less are considered Non-Standby Service Customers and exempt from paying
standby charges. Please see Attachment No. 1-Definitions for more information regarding
Non-Standby Service Customers
.
3.
Enters into a contract for services related to its generator. Contracts will be made for this
service provided the Company has sufficient capacity available in production, transmission
and distribution facilities to provide such service at the location where the service is
requested.

The Company delivers 60 hertz, single or three-phase, alternating current service at transmission,
primary or secondary voltage under this rate schedule, supplied through one meter.

As available and at the Companys option, such service shall be supplied at available voltage. All
equipment to be served must be of such voltage and electrical characteristics that it can be served
from the circuit provided for the main part of the load. The electricity used must be able to be
properly measured by the meter ordinarily installed on such a circuit. If the equipment to be served
is such that this is impossible, the customer must provide any necessary transformers,
autotransformers, or other devices suitable for connection to the circuit provided by the Company.



Otter Tail Corporation d/b/a

OTTER TAIL POWER COMPANY
Vol. I, Sheet 40
Fergus Falls, Minnesota
Rate Designation C-10M, Page 2 of 8
ELECTRIC RATE SCHEDULE
Third Revision



MINNESOTA PUBLIC
EFFECTIVE for services rendered on
UTILITIES COMMISSION
and after, November 30, 2007, in MN
Docket No. E-017/GR-07-1178

Approved: November 27, 2007
APPROVED: Bernadeen Brutlag


Manager, Regulatory Services


STANDBY SERVICE (Continued)

Intermittent and highly fluctuating loads may require a separate service line or transformer and
separate metering and billing. Power production equipment at the Customer site shall not operate in
parallel with the Companys system until the installation has been inspected by an authorized
Company representative and final written approval is received from the Company to commence
parallel operation.

STANDBY RATE OPTIONS - FIRM AND NON-FIRM

OPTION A: FIRM STANDBY

Transmission Primary Secondary


Service
Service Service
FIRM STANDBY FIXED CHARGES:

Customer Charge $ 120.00/mo $ 120.00/mo $ 120.00/mo

Standby charge per month per kW
of Contracted Backup Demand


$ 4.99/kW $ 5.22/kW $ 5.47/kW




FIRM STANDBY ON-PEAK DEMAND CHARGE

Metered Demand per day per kW
On-Peak Backup Charge $0.36/kW $0 .37/kW $0.39/kW

















Otter Tail Corporation d/b/a

OTTER TAIL POWER COMPANY
Vol. I, Sheet 40
Fergus Falls, Minnesota
Rate Designation C-10M, Page 3 of 8
ELECTRIC RATE SCHEDULE
Third Revision



MINNESOTA PUBLIC
EFFECTIVE for services rendered on
UTILITIES COMMISSION
and after, November 30, 2007, in MN
Docket No. E-017/GR-07-1178

Approved: November 27, 2007
APPROVED: Bernadeen Brutlag


Manager, Regulatory Services


STANDBY SERVICE (Continued)

FIRM STANDBY ENERGY CHARGES

Energy Charges per kWh
On-peak Charge $ 0.04068 0.04131 $ 0.04194
Off-Peak Charge $ 0.03043 $ 0.03081 $ 0.03123

OPTION B: NON-FIRM STANDBY
Transmission Primary Secondary


Service
Service Service

NON-FIRM STANDBY FIXED CHARGES:

Customer Charge $ 120.00/mo
$ 120.00/mo
$ 120.00/mo

Standby charge per month per kW
of Contracted Backup Demand $ 0.00/kW $ 4.50/kW $ 4.73/kW

-R-
-R-

STANDBY RATE OPTIONS, OPTION B: NON-FIRM (continued)

NON-FIRM STANDBY ENERGY CHARGES:

Transmission Primary Secondary


Service Service Service
Energy Charges per kWh
On-peak Charge Not Available Not Available Not Available
Off-Peak Charge $ 0.03043 $ 0.03081 $ 0.03123








-R-

INTERIM RATE ADJUSTMENT
While the MPUC considers our request, state law allows us to collect higher rates on an interim
basis. A 5.41 percent increase will be added to the sum of the following, as applicable: Customer
Charge, Energy Charge, Demand Charge, Fixed Charge, and the monthly Minimum Charge. If final
rates are lower than interim rates, we will refund customers the difference with interest. If final
rates are higher than interim rates, we will not charge customers the difference.

-N-
-N-
-N-
-N-
-N-
-N-
MONTHLY MINIMUM CHARGE:

The sum of the Customer Charge and the Standby Charge
for Contracted Backup Demand.


Otter Tail Corporation d/b/a

OTTER TAIL POWER COMPANY
Vol. I, Sheet 40
Fergus Falls, Minnesota
Rate Designation C-10M, Page 4 of 8
ELECTRIC RATE SCHEDULE
Third Revision