Edition of 1-1-00 Page 1 of 21 BASIS FOR USE OF RECURRING SPECIAL ...


Page 1 of 21
BASIS FOR USE
OF RECURRING SPECIAL PROVISIONS
AND RECURRING PLAN DETAILS
CODE
Description
Date
BASIS FOR USE
100-C-146
Payment of Predetermined Minimum Wage (Davis-Bacon) IN970001
A 6-06-97
ALL PROJECTS IN LAKE, LAPORTE, PORTER, AND ST. JOSEPH COUNTIES
EXCEPT BUILDING CONSTRUCTION.
100-C-147
Payment of Predetermined Minimum Wage (Davis-Bacon) IN970006
A 6-06-97
ALL PROJECTS IN COUNTIES OTHER THAN LAKE, LAPORTE, PORTER, AND ST.
JOSEPH EXCEPT BUILDING CONSTRUCTION.
100-C-148
Payment of Predetermined Minimum Wage (Davis-Bacon) ________
A 6-06-97
ALL BUILDING CONSTRUCTION - DETERMINED BY CENTRAL OFFICE PERSONNEL
100-C-150
Use of the Word Bituminous
A 9-05-97
ALL CONTRACTS
100-C-151
Federally Funded Contract with DBE
R 1-04-99
AS DETERMINED BY CONTRACTS SECTION
100-C-152
Federally Funded Contract without DBE
R 1-04-99
AS DETERMINED BY CONTRACTS SECTION
100-C-159
Year 2000 Terms
2-08-99

ALL CONTRACTS
100-C-160
1999 Standard Specifications
2-10-99

ALL CONTRACTS
101-B-042
Structure Numbers for Pay Items
R 9-1-93
MORE THAN ONE BRIDGE FILE NUMBER IN CONTRACT, AND LUMP
SUM PAY ITEMS SHOWN TO BE REQUIRED FOR EACH SUCH BRIDGE FILE
102-C-082
Schedule of Pay Items for Alternate Bids
R 1-04-99
PAY ITEMS IN CONTRACT WHICH REQUIRE ALTERNATE BIDS
102-C-145
Toll Road Special Provisions
R 1-04-99
ALL TOLL ROAD CONTRACTS
103-C-036
Owners' and Contractors' Protective Liability Insurance
R 1-04-99
Coverage for Operations of the Designated Contractor
ALL FEDERAL AID LOCAL PUBLIC AGENCY CONTRACTS
104-C-139
Geotechnical Evaluation Report
A 9-19-95
GEOTECHNICAL REPORT HAS BEEN DEVELOPED AND APPROVED
104-R-168
Schedule of Operations and Traffic Control for Undersealing,
R 1-04-99
Concrete Patching, Placing Underdrains, and Resurfacing
PAVEMENT UNDERSEALING, PATCHING, SHOULDER DRAIN PLACEMENT,
AND RESURFACING SPECIFIED
105-C-056
Engineer Application Personal Computer
R12-09-98
ALL CONTRACTS Edition of 1-1-00
Page 2 of 21
105-C-071b
Fax Machine in Field Office (Advanced Features)
R 1-04-99
AS DETERMINED NECESSARY BY DISTRICT CONSTRUCTION
105-R-305
Pipe Structure Pay Items
R 1-04-99
ALL CONTRACTS WITH PIPE STRUCTURE PAY ITEMS
106-C-074
Basis for Use of Approved or Prequalified Materials
R 1-04-99
ALL CONTRACTS
106-R-276
Protection and Restoration of Established Vegetation
R 1-04-99
ALL BRIDGE, ROAD, AND RESURFACE CONTRACTS
107-B-040
Environmental Restrictions
R 1-04-99
AS DETERMINED BY PROJECT DESIGNER
107-C-029
Equal Employment Opportunity Trainees
R 7-14-98
AS DETERMINED BY CONTRACT SERVICES
107-C-051
U.S.Army Corps of Engineers Permit
R 1-04-99
AS DETERMINED BY PROJECT DESIGNER
107-C-112
Traffic Control Changes and On-Call Maintenance of Traffic
R 3-04-99
Control Devices
TRAFFIC BEING MAINTAINED ON PRESENT ROADWAY WITH NO WATCHMAN
REQUIRED
107-R-042a
Railroad Information
R 1-04-99
HIGHWAY OVER OR UNDER RAILWAY
107-R-042b
Protection of Railway Interest
R10-08-96
AS DETERMINED BY UTILITIES SECTION
107-R-169
Statements About Existing Conditions of Utilities, Additional
Right-of-Way, and Encroachments
R 1-04-99
ALL CONTRACTS
108-C-043
Incentive or Disincentive for Opening Project to Traffic
R 1-04-99
Ahead
of Schedule
AS DETERMINED NECESSARY BY DEPARTMENT PERSONNEL WHO SET
CONTRACT TIME
108-C-078
Partnering Overhead
R 7-14-98
AS DETERMINED NECESSARY BY DISTRICT CONSTRUCTION
108-C-089
Percentage of Work Required of Prime Contractor
R 1-04-99
AS DETERMINED BY CONTRACT SERVICES PERSONNEL WHO WILL PROCESS
CONTRACTS SHORTLY BEFORE LETTING
108-C-090
Latest Date to Begin Work
R 1-04-99
DELAYED START OF WORK DESIRED
108-C-091
Failure to Complete on Time for Restriction-One Structure
R 1-04-99
LANE RESTRICTIONS ON ONE LANE, PHASE, OR DIRECTION
108-C-092
Failure to Complete on Time for Restriction-Two or More Structures
R 1-04-99
LANE RESTRICTIONS ON MORE THAN ONE STRUCTURE, PHASE, OR
DIRECTION Edition of 1-1-00
Page 3 of 21
108-C-093
Failure to Complete on Time for Road Closure
R 1-04-99
AS DETERMINED NECESSARY BY DEPARTMENT PERSONNEL WHO SET
CONTRACT TIME FOR CONTRACT WHICH INCLUDES DETOUR
108-C-094
Failure to Complete on Time for Intermediate Completion Date
R 1-04-99
AS DETERMINED NECESSARY BY DEPARTMENT PERSONNEL WHO SET
CONTRACT TIME FOR CONTRACT IN WHICH A CERTAIN PORTION OF THE
WORK IS TO BE COMPLETED BEFORE THE ENTIRE CONTRACT IS
108-C-095
Failure to Complete on Time for Calendar Completion Date
R 1-04-99
AS DETERMINED NECESSARY BY DEPARTMENT PERSONNEL WHO SET
CONTRACT TIME
108-C-096
Failure to Complete on Time for Work Days
R 1-04-99
AS DETERMINED NECESSARY BY DEPARTMENT PERSONNEL WHO SET
CONTRACT TIME
108-C-127
Earliest Date To Begin Work
R 1-04-99
AS DETERMINED NECESSARY BY DISTRICT CONSTRUCTION
108-L-001
Notice to Proceed With Demolition Work
R 1-04-99
PAY ITEMS: 202-03000 HOUSES AND BUILDINGS PARCEL NO. ____
REMOVE
108-L-012
Specialty Pay Items
A 12-1-93
PAY ITEM: 202-01261 TESTING FOR ASBESTOS REMOVAL
108-R-148
Construction Equipment in Park Areas
R 1-04-99
PARK CONTRACT
112-C-122
State Funded Contract with Davis-Bacon Wage Rates
R 1-04-99
AS DETERMINED BY CONTRACTS SECTION
201-C-052
Clearing Right-of-Way
R 1-04-99
PAY ITEMS FOR CLEARING RIGHT-OF-WAY
201-M-030
Debris Removal at Bridge Structures
R 1-04-99
DEBRIS REMOVAL MAINTENANCE CONTRACT
201-R-021
Burning of Natural Growth Permitted
R 2-21-90
IDEM HAS ISSUED PERMIT TO DEPARTMENT FOR BURNING OF NATURAL
GROWTH
201-R-179
Air-Curtained Open-Pit Incineration of Natural Growth Required
R 2-21-90
IDEM HAS ISSUED PERMIT TO DEPARTMENT FOR BURNING BY MEANS OF
AIR-CURTAINED OPEN-PIT INCINERATOR
202-L-013
Inspection and Testing for Asbestos Material
1-13-99

AS DETERMINED BY PRE-ENGINEERING AND ENVIRONMENT
203-B-025
Marion County Borrow Pits
R 1-04-99
PROJECT LIMITS IN MARION COUNTY, PAY ITEM: 203-02070 BORROW
203-R-121
Borrow Pit Wetland Enhancement
R 1-04-99
BORROW PIT EXCAVATION EXPECTED TO REACH WATER TABLE
203-R-155
Rock Backfill
R 1-04-99
PAY ITEM: 202-92634 ROCK BACKFILL Edition of 1-1-00
Page 4 of 21
203-R-205
Wetland Identification
R 1-04-99
COMMON EXCAVATION QUANTITY EXCEEDS BORROW QUANTITY
203-R-260
Linear Grading
R 1-04-99
PAY ITEM: 203-90014 OR 203-02080 LINEAR GRADING. EARTH
WEDGING AT OUTSIDE EDGE OF SHOULDER OR BEHIND GUARDRAIL, OR MEDIAN
EARTH FILLING
203-R-286
Excess Excavated Materials Disposal Site
R 1-04-99
WASTE MATERIAL TO BE DISPOSED OF OUTSIDE OF RIGHT-OF-WAY
203-R-360
Embankments Constructed of Coal Combustion By-Products
A 4-08-98
PAY ITEM OF 3800 CUBIC METERS (5000 CYS) OR MORE OF BORROW
204-R-049
Piezometers
R 1-04-99
PAY ITEM: 204-02295 PIEZOMETER
206-B-026
Steel Sheet Piling at Railroad Grade Separation
R 1-04-99
STEEL SHEET PILING REQUIRED, RAILWAY WITHIN PROJECT LIMITS
206-B-113
General Bridge Requirements
R 1-04-99
BRIDGE REPLACEMENT OR NEW BRIDGE CONSTRUCTION
208-R-111
Gore Area Treatment
R 1-04-99
PAY ITEM: 203-02046 GRADING OF GORE AREA
E 211-BFIL-03
Backfill Placement For Substructures
A 7-27-99
AS DEEMED NECESSARY BY THE PROJECT DESIGNER
211-R-357
B Borrow and B Borrow for Structure Backfill
R 9-11-98
PAY ITEMS: B BORROW OR B BORROW FOR STRUCTURE BACKFILL
E 303-SHDR-01
Shoulder Drain
A 1-02-98
PAY ITEM: AGGREGATE FOR SHOULDER DRAIN
303-M-002
Shoulders Adjacent to Resurface Work
R 1-04-99
RESURFACE CONTRACT WITH UNPAVED SHOULDERS
E 303-STRW-01
Shoulder Treatment for Resurfacing Work
R 1-02-98
DRAWING FOR RESURFACE CONTRACT WITH UNPAVED SHOULDERS
304-R-199
Subbase for Cement Concrete Pavement
R 7-19-99
PAY ITEM: 304-04403 SUBBASE FOR CEMENT CONCRETE PAVEMENT
304-R-248
Recycling Existing Concrete Pavement as Compacted Aggregate
R 1-04-99
WHEN DETERMINED NECESSARY BY DISTRICT CONSTRUCTION
305-R-139
Partial Depth Joint Patching With HMA Mixtures
R 8-14-97
PAY
ITEM: 305-04346 JOINT PATCHING MATERIAL HV
E 305-RLTC-01
Retrofit Load Transfer
A 9-01-99
PAY ITEM: RETROFIT LOAD TRANSFER
E 305-RLTC-02
Retrofit Load Transfer
A 9-01-99
PAY ITEM: RETROFIT LOAD TRANSFER
311-R-229
Cement Concrete Pavement Cracking and Seating
R 3-04-99
PAY ITEM: CONCRETE PAVEMENT CRACKING AND SEATING Edition of 1-1-00
Page 5 of 21
E 400-PTRN-01
Pavement Type Transition
A 9-01-99
JOINTING NEW ASPHALT PAVEMENT TO EXISTING PCCP
400-R-366
HMA Revised
R 7-16-99
ALL CONTRACTS WITH HMA PAY ITEMS
401-R-324
Plant Laboratory for Plant Mix Pavements
R 8-14-97
AS DETERMINED BY DISTRICT CONSTRUCTION
402-R-295
Micro-Surfacing
R 8-14-97
PAY
ITEM OF MICRO-SURFACING
E 402-SHCG-02
Milled HMA Shoulder Corrugations
A 9-01-99
PAY ITEM: MILLED HMA CORRUGATIONS
E 500-PTRN-01
Pavement Type Transition
A 9-01-99
JOINTING NEW PCCP TO EXISTING HMA
E 500-PTRN-02
Pavement Type Transition
A 1-03-00
JOINTING NEW PCCP TO EXISTING PCCP WITH OVERLAY
E 500-PTRN-03
Pavement Type Transitions
A 9-01-99
JOINTING NEW PCCP TO EXISTING PCCP WITH OVERLAY
E 500-PTRN-04
Pavement Type Transitions
A 9-01-99
JOINTING NEW PCCP TO EXISTING PCCP
E 500-SHCG-01
Formed PCCP Shoulder Corrugations
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 500-SHCG-02
Milled PCCP Shoulder Corrugations
A 9-01-99
PAY ITEM: MILLED PCCP CORRUGATIONS
E 501-CCPJ-11
Pavement Joint Use
A 1-02-98
PAY ITEM: QC/QA-PCCP OR PCCP
E 503-CCPJ-01
Type D-1 Contraction Joint
A 9-01-99
PAY ITEMS:QC/QA-PCCP OR PCCP
E 503-CCPJ-02
Longitudinal Joint
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 503-CCPJ-03
Longitudinal Joint
A 9-01-99
PAY ITEMS: QC/QC-PCCP OR PCCP
E 503-CCPJ-04
Longitudinal Keyway Joint
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 503-CCPJ-05
Transverse Construction Joint
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 503-CCPJ-06
Transverse Joint Seals
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 503-CCPJ-07
Longitudinal Construction Joint
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP
E 503-CCPJ-08
Longitudinal Construction Joint
A 9-01-99
PAY ITEMS: QC/QA-PCCP OR PCCP Edition of 1-1-00
Page 6 of 21
E 506-CCPP-01
Concrete Pavement Patch Details
A 9-01-99
PAY ITEM: PCCP PATC