Cable Plant Week of
June 4, 2004
Russells Report:
The summary of my weeks activities are:
Housing time clock project: The contractors portion
of this project is completed, insofar as the original project deliverables.
Housing may slightly amend the project, due to changes in vendor offerings.
The installation of the additional telco cable between
coll. 9 ADF and the student Health Center has the cable installed and
terminated. The testing and physical inspection (punch list) is all
that remains.
I will attend seminars at Graybars vendor show this
Thursday.
Reviewing and gathering budgetary costs for the Chancellor
relocation.
The report has been completed and forwarded, awaiting
comment from the relocation committee.
We have been asked to comment on the following:
a. Basement closet recommendations and cost of utilizing
existing versus new closet in the vertical 'stack'
b. Recommendations for a situational room (data /
voice/ media). This room is proposed to be located on the 2nd floor.
Humanities Bldg.
This project has gone to bid without allowing me
to assure changes to the drawings and spec book were accurate. There
are numerous mistakes. I will do a complete review of the bid documents.
Insofar as retaining the third copper cable in the
Humanities project and/or all future projects, the project has gone
to bid with the third cable optional and bid as an addition to the project.
We still need to meet with PP&C and the users
of the building.
Baskin / engineering Building, working with Baskin
staff to get fiber installed between Baskin and E2. Presently determing
final fiber requirements and designing the Baskin 0.1 closet. This project
will be managed by Cable plant as a small cabling project.
Engineering Building: Some items have slipped through
the submittal process (CATS was unable to review). I am working with
the contractor and PP&C towards workable solutions.
Housing Admin / Staff Art studio project: This project
was performed without knowledge of CATS. Several issues remain outstanding.
Reviewing construction documents for the following
projects:
ERC 50% construction
Biomedical Research Facility
PSB submittals
Humanities Bldg.
SBC CAMFAC cable install. coordinating activities
between SBC and Jim Gabrio to get the conduit installed. SBC will saw
cut the concrete into the above ground splice can. CAMFAC will dig the
trench and install the conduit. I am obtaining a schedule from CAMFAC
to coordinate the efforts.
Thimann 191 / Lick Expansion:
No word from Jeff Mallory regarding his plans to
extend the Lick network into Kerr 191.
East Field House to OPERS cable replacement:
Reviewing pathways and sizing cable to determine
method of replacement.
Porter ADF to Oakes cable removal, project to start
in June.
Marys report:
Project listing 06/02/04
Investigating setting up Pinnacle to better track data needed for
the small wiring projects. The new database is very complex, documentation
is vague, therefore reading and experimentation in the test database
is necessary to accomplish this task. Implemented a process in
the test database for Marcy & Neil to test.
5/20 Awaiting
final ok from Marcy. Marcy to schedule time in early June for us to
meet and finalize this project.
5/27 no change
6/2 Still waiting
for Marcy to schedule on Cruztime.
Investigating some Oracle code that will turn SQL into html.
Just ran across it, cant definitely say, yet, if it will be of value
to us, for Pinnacle. Will play around with it and let you know.
- 6/2 Havent investigated, yet.
3. Finished implementing
new web style from PIO. Plan to go live, June 3.
New bldg jack/cable numbering.
6/2/04 Need
to input jacks for Moffett Park. Asked Mike to provide copies
of his docs.
5.
Still no word as to when the fiber inventory project will be given any
priority and reassigned a technician.
6. Neil
working on small cable projects white paper. Projected due data
of June 4<sup>th.
FYI, Media services are interested in accessing Pinnacle for their
needs. Theyll schedule some time when they are available.
Labeled CTV jacks in PSB,
will inventory them, with rest.
Found database glitch in FDX, for floor numbering. Their DBA
is working on it.
- 06/02. I Havent checked
to see if fix was implemented.
Neils report:
Small Cable Projects:
Writing small cable project web page.
NW 254 - 1 Comm Bldg. Did contractor walkthrough. Cyclops to bid. Received
and forwarded bid. Waiting for customer.
NW 258 - 1 Hahn. Did contractor walkthrough. Project completed.
NW 264-1 College 9. Scott Loosley. Did contractor walkthrough. Waiting
for customer approval.
NW 265-1 CNG project for Joshepine Ortega. TMS rebid project. Customer
now wants to modify job.
NW 266-1 CFaO for Jeff Duncan. Did contractor walkthrough. Waiting for
customer approval.
Capital projects:
Engineering 2:
I have been working with PP&C and Rosendin on outstanding
issues and doing inspections. I lead one more tour for NTS.
Project is nearing completion. Outstanding items include:
Installing cabling in several concrete-filled floor monuments on 2nd
and 5th floor.
Installing cabling in several locations where conduit was not installed
by electrical contractor.
Some labeling.
Audio visual work.
Stevenson Infill:
Project is nearing completion. All station and most backbone cabling
is completed. Inspections continue. I have been acceptance-testing station
cabling in buildings 41 and 43. Data cabling is showing few errors.
Voice cabling labeling and voice backbone errors are being corrected
by contractor. Fiber backbone termination is under way. I am assembling
a punchlist.
Porter Infill, Cowell Infill:
Most station and backbone cabling is complete. Closet layout is complete.
Inspections continue. We have not yet begun acceptance-testing cabling.
PSB
Cabling of PSB begins this week. Contractor has submitted faceplate/jack
sample.
Student Health:
Student Health center 100-pair installation: Acceptance testing
in progress.